Oso Parkway
Spoke to Karl, they will mobilize to backfill RW2 tomorrow or the day after. Kenneth and Mike clarified a staging issue with them. Victor is working on getting approval for steel spliced piles where the batter will create a situation where driving might occur over rail tracks. Concrete splicing does not appear to be practical given our time constraints. Sacramento requires project specific analysis which would have to be provided by CH2M Hill. Neither CH2M Hill nor Sacto appears to be eager to go this route.