Crown Valley - Broke into top of 2' diam RCP drain pipe @ 19 feet deep, elevation 271.6'. Hole in pipe approx 1' by 2', rebar remains in place. 4.5' diameter drilled hole for east CIDH pile for sign 100 foundation. Cancelled pour, did not set rebar, covered hole with plywood and caution tape.
The drainage pipe runs along the outer edge of the pile on the northeast side.
It needs to be repaired and the sign either needs to be shifted or the pile shortened. We also need to determine the impact on the drain pipe.