Contractor's meeting for Oso
RW2 backfill next week. Discussed removing shoring box while backfilling. Karl (Ortiz) said they would pull the shoring box out a few feet at a time, backfilling as they went, for safety reasons. They will address the RW5 compaction problems at that time as well.
Victor will be able to provide an estimate of lead time for changing Abutment 1 footing design to concrete spliced piles or to welded metal pipe piles by next week.
Copies of Twinings reports of concrete core breaks on RW2 footing to Gary.
Copies of RR questions to Ortiz, to be copied to Victor.
Victor will review Bent 2 pile driving plan separately from Abut 1, to allow Ortiz to move forward on Bent 2 if it is ready before Abut 1.
John (Ortiz) will ask Foundation Pile for their time requirements as well as an estimate of costs for change in Abutment 1 footing piles.