Tuesday, May 19, 2009
d
Reviewed the specs regarding galvanizing vs painting sign structures. Caltrans requires galvanizing. However the specs also require painting. Karim spoke to Costa Mesa, they do not wish to enforce that spec. They will go with CT galvanizing only.
crown 12-0F8204- finish accepted
CCO getting reviewed.
--
==================================================================
This mobile text message is brought to you by AT&T
Monday, May 18, 2009
55 widen
Spoke to Karim, METS re galvanizing vs painting of sign struct. Will email w CT policy after reviewing specs
Oso 12-0E0704
(Oso 12-0E0704) spoke to Karl, re rw2 backfill. Ready to start when his crew comes back from another job. Front of rw5 still not compacted appropriately. Pauls crew fabbing panels for rw3 stem. Integrity standing cages for rw3.
Friday, May 15, 2009
Thursday, May 14, 2009
Multimedia message
oso - victor took names, stem rw build,
Crown - getting approval of drainage patch
Crown - getting approval of drainage patch
I am at re offsite mtg
Wednesday, May 13, 2009
Oso
Ortiz is backfilling final layer for RW 4 and 5. I asked Victor to call in a compaction test for 10am tomorrow. Otherwise it is just Integrity steel and Paul's crew working on the rw3 stem.
crown
Discussed hydraulic requirements for repair of drain pipe with Roger Koa and Mylinh Duvan. Drew a detail and researched the proprietary product that they recommended for the repair. Emailed to Bose, Andy, Mylinh and Roger for their review prior to directing Odonnell to perform.
crown
Integrity on site, pauls crew fabricating panels, karls crew working on subgrade along rws 4 and 5
Tuesday, May 12, 2009
Oso
start stem rw3 install steel. Integrity guillermo aguirre l: joseph hernandezIA: javier ramos I -8...level pad for crane operator bob vierstra -cat 966g -4
Crown Valley widening
ACL came and placed 220 ft of type 60 and 120 ft of type 736 brail. Directed Odonell to start repairs to drainage pipe, damaged during CIDH drilling. Spoke to Nadeem Srour and Sam Sukasian, geotech; MyLinh Duvan, hydraulics; Aun Tran, project engineer; Kenneth Oh and Bose P, district construction to try to come to a consensus on what the best way of dealing with the sign 100 foundation.
ACL came and placed 220 ft of type 60 and 120 ft of type 736 brail. Directed Odonell to start repairs to drainage pipe, damaged during CIDH drilling. Spoke to Nadeem Srour and Sam Sukasian, geotech; MyLinh Duvan, hydraulics; Aun Tran, project engineer; Kenneth Oh and Bose P, district construction to try to come to a consensus on what the best way of dealing with the sign 100 foundation.
Monday, May 11, 2009
Oso Parkway
Spoke to Karl, they will mobilize to backfill RW2 tomorrow or the day after. Kenneth and Mike clarified a staging issue with them. Victor is working on getting approval for steel spliced piles where the batter will create a situation where driving might occur over rail tracks. Concrete splicing does not appear to be practical given our time constraints. Sacramento requires project specific analysis which would have to be provided by CH2M Hill. Neither CH2M Hill nor Sacto appears to be eager to go this route.
Irvine Approach Slabs
Met with Nabil Ruda, Bang Nguyen and All American Asphalt to discuss reopening the project. Grades are set. AAA will provide a new scedule and call surveyors to provide grades as shown on the revised project plans. Nabil will work on CCOs to provide days due to delays caused by grade revision. AAA intends to grind out 12" of AC and to place PCC, instead of removing all and replacing with rapid set. CT is ready to start.
Friday, May 8, 2009
Crown Valley - Broke into top of 2' diam RCP drain pipe @ 19 feet deep, elevation 271.6'. Hole in pipe approx 1' by 2', rebar remains in place. 4.5' diameter drilled hole for east CIDH pile for sign 100 foundation. Cancelled pour, did not set rebar, covered hole with plywood and caution tape.
The drainage pipe runs along the outer edge of the pile on the northeast side.
It needs to be repaired and the sign either needs to be shifted or the pile shortened. We also need to determine the impact on the drain pipe.
The drainage pipe runs along the outer edge of the pile on the northeast side.
It needs to be repaired and the sign either needs to be shifted or the pile shortened. We also need to determine the impact on the drain pipe.
Thursday, May 7, 2009
Multimedia message
I movedthe sign pedestals up 6". The high pt of the rd under the sign is 292.95- plan top of plate 290.8=2.15'....H
Multimedia message
Moved transition. Now ends @ sta 43+70. Instead of beginning there. Otherwise transition is off of wall w/o foundation. Type 60 does not need footing and is same H for safety.
Wednesday, May 6, 2009
Tuesday, May 5, 2009
Oso
Aggregate passed test. Pour on for tomorrow. Notified Ernest Delgado (Ortiz). Called John Britt (Ortiz) asked to be copied in on RR to Ortiz correspondence re shoring and Twinings results. Victor did not have copies.
Contractor's meeting for Oso
RW2 backfill next week. Discussed removing shoring box while backfilling. Karl (Ortiz) said they would pull the shoring box out a few feet at a time, backfilling as they went, for safety reasons. They will address the RW5 compaction problems at that time as well.
Victor will be able to provide an estimate of lead time for changing Abutment 1 footing design to concrete spliced piles or to welded metal pipe piles by next week.
Copies of Twinings reports of concrete core breaks on RW2 footing to Gary.
Copies of RR questions to Ortiz, to be copied to Victor.
Victor will review Bent 2 pile driving plan separately from Abut 1, to allow Ortiz to move forward on Bent 2 if it is ready before Abut 1.
John (Ortiz) will ask Foundation Pile for their time requirements as well as an estimate of costs for change in Abutment 1 footing piles.
RW2 backfill next week. Discussed removing shoring box while backfilling. Karl (Ortiz) said they would pull the shoring box out a few feet at a time, backfilling as they went, for safety reasons. They will address the RW5 compaction problems at that time as well.
Victor will be able to provide an estimate of lead time for changing Abutment 1 footing design to concrete spliced piles or to welded metal pipe piles by next week.
Copies of Twinings reports of concrete core breaks on RW2 footing to Gary.
Copies of RR questions to Ortiz, to be copied to Victor.
Victor will review Bent 2 pile driving plan separately from Abut 1, to allow Ortiz to move forward on Bent 2 if it is ready before Abut 1.
John (Ortiz) will ask Foundation Pile for their time requirements as well as an estimate of costs for change in Abutment 1 footing piles.
Monday, May 4, 2009
Friday, May 1, 2009
Multimedia message
Forming on rw 3 footing still needs work. Footing steel not complete. Done up to 16+60. Still working out dirty agggregate issues w cemex.
Thursday, April 30, 2009
Wednesday, April 29, 2009
Tuesday, April 28, 2009
Monday, April 27, 2009
Friday, April 24, 2009
Thursday, April 23, 2009
Wednesday, April 22, 2009
Saturday, April 18, 2009
Friday, April 17, 2009
Thursday, April 16, 2009
Wednesday, April 15, 2009
Multimedia message
paul navarro 16 hours, basilio juan martin: lab for aurelio arevalo, cm eric camacho, cm hugo cabrerra, lab jesus viramontes, merli 28 m pump - steiner pump operator 4hours for all but pauls crew 8 hours for them
Tuesday, April 14, 2009
Hi Paul, Chked footing
Crown rw1 footing
1st step clr to soil ..need to pop out forms evrywhere..2nd step-top mat out of pour: clean out bottom
1st step clr to soil ..need to pop out forms evrywhere..2nd step-top mat out of pour: clean out bottom
Multimedia message
Backfill operation @ crown deere excav jesse gonzales eric alvarez ernie ventura everardo zuniga neil-9097725042 dan from ct
Monday, April 13, 2009
Multimedia message
Oso rw 1 - integrity rebar placers, footing steel 13+25 to end ; dennis mcguireF scott wheatonI, ryan youmansI, giovanni rivieraI ; T16W 18OC
Friday, April 10, 2009
Multimedia message
Crown shooting tow grades for barrier acl. Electrical then ironworkers, clean up : msl electric-tim sullivan f, jeff? elec, manuel villagrana elec: o'donnell prime everardo zuniga- foreman, Jesse gonzalez, ernest ventura,
united rentals wacker, water buffalo trailer
sam ct elec came out
Thursday, April 9, 2009
Wednesday, April 8, 2009
Multimedia message
Excavator damaged electrical wiring, Moore electric out to fix
Still need clean out, keyway raveling, steps not sharp
Tuesday, April 7, 2009
Multimedia message
Forming rw1 from e0 owen teeter c- gave tow grades, martin vasquez ca, basillio pecheco c, bernardo gatica c, juan miranda ca, multiquip 5000 generator, wrk truck
Monday, April 6, 2009
Friday, April 3, 2009
Today
Oso RW grades. Drew up on Microstation, Approved Sign submittal for 55 widening - Discussed with Karim, diary for Neelima's sign job,
Thursday, April 2, 2009
Wednesday, April 1, 2009
Multimedia message
Reminded to push down tie wire at face of wall. Reminded them of expansion joint. Looks good. Forming in bac at bottom at weakened plane joints, not flush.