d

Reviewed the specs regarding galvanizing vs painting sign structures. Caltrans requires galvanizing. However the specs also require painting. Karim spoke to Costa Mesa, they do not wish to enforce that spec. They will go with CT galvanizing only.
1/2 (oso contractors mtg) held at ortiz office. Informed ortiz of sign/power line clearance issue. Abut 1 footing redesign w/ ham

--
==================================================================
This mobile text message is brought to you by AT&T

2/2 aguchi and ch2m. Fp owes us request for change re splicing of piles. And est cost of H piles.

--
==================================================================
This mobile text message is brought to you by AT&T

crown 12-0F8204- finish accepted

CCO getting reviewed.

--
==================================================================
This mobile text message is brought to you by AT&T

Monday, May 18, 2009

55 widen

Spoke to Karim, METS re galvanizing vs painting of sign struct. Will email w CT policy after reviewing specs
Crown, spoke to Everardo, 4man. Told him not to commence repair of drain pipe without detail provided to Neil, owner. Sent letter formalizing direction to perform repair per detail approved by hydraulics and geotech that was previously provided by email.

Turned Estimates in to Bose. Started CCO.

Oso 12-0E0704

(Oso 12-0E0704) spoke to Karl, re rw2 backfill. Ready to start when his crew comes back from another job. Front of rw5 still not compacted appropriately. Pauls crew fabbing panels for rw3 stem. Integrity standing cages for rw3.