Friday, February 27, 2009
Thursday, February 26, 2009
Wednesday, February 25, 2009
vista hermosa mtg w/peterson chase
discussed cost adjustment and liquidated damages. Went back and recalced quantity of poly furnished based on 450batches agreed upon.
Irvine approach slabs
Call Nabil, should we nail down grades, spoke to AAA talking about restarting job in April
55 widening
Issues in meeting today
-retaining curb? Seems to have little protection against overturning...will ask about review on this issue
-drainage drawings?
-submittal 4, I have no issues with it ..email Kausi w/ status
-foundation placed last night
-wall will be placed next week
-asked tom for diaries, he said he would email
-retaining curb? Seems to have little protection against overturning...will ask about review on this issue
-drainage drawings?
-submittal 4, I have no issues with it ..email Kausi w/ status
-foundation placed last night
-wall will be placed next week
-asked tom for diaries, he said he would email
Friday, February 20, 2009
55 widening
Texted Karim "Template for steel installed. Do we have a date for a compaction test? Are the steelworkers scheduled? Thanks!"
Thursday, February 19, 2009
Wednesday, February 18, 2009